You are here: Home > Bangladesh
All posts from

onlineapplication.dpdc.org.bd Apply For Online New Connection Bangladesh : Dhaka Power Distribution Company

Organization : Dhaka Power Distribution Company Limited (DPDC)
Facility Name : Apply For Online New Connection
Country: Bangladesh
Website : https://onlineapplication.dpdc.org.bd/home.php

Sponsored Links:
Want to comment on this post?
Go to bottom of this page.

DPDC Online New Connection Bangladesh

Application for Industrial connection through Bangladesh Investment Development Authority (BIDA)’s Online One-Stop Service System

Related / Similar ServiceDPDC Find Your Clearance / Arear Bill Certificate

Sponsored Links:

The application process through BIDA One Stop Web Portal for Industrial connection has been launched on 31th December 2020. Investors are requested to register and apply through BIDA Webportal (bida.gov.bd) of Industrial Connection for faster service.

Advantages

** Investors can easily get electricity connection as well as other services through single online platform

** Investors in the area covered by DPDC can easily submit the required documents and apply for new electricity connection along with other services from BIDA Web Portal

** Monitoring the status of the Online Application
** SMS after each step is completed
** Investors can easily get electricity connection within the stipulated timeline by paying new connection fee through online system of Sonali Bank.

Steps of Online Application

Step 1 : Click on Application for New Connection at the right-side panel of DPDC website. Then go to the “Apply New Application” link and a page for initial information will be arrived.

After fill up the page with appropriate information please enter Save button. Immediately, a short message will send to entered mobile number along with tracking number and pin number.

Besides that, prospective customer will be requested for his/her confirmation. Applicant can update entered information before his/her confirmation but not permitted after that.

After the confirmation, there will be an application form displayed on the screen and customer should printout the same. Applicant should put his/her signature on the form and submit to respective NOCS office.

Moreover, prospective customer can monitor his current application status via website or SMS service by using this tracking number.

Step 2 : For LT connection, prospective customer will be requested to submit the following documents via SMS

1. Printout application along with signature of the prospective applicant,
2. 1 (one) copy of Passport size color photo
3. Photocopy of National ID

4. Land Ownership Document/Lease Deed/Namazari Paper, The Inheritance Certificate in the absence of Original Owner
5. Copy of paid bill, if previously connected (there are no new documents needed to get more connections in the same name/place)

6. Fire extinguishing certificate in multi-storied building (more than 10 stories)
7. City corporation/municipality approved Building plan, holding number, in RAJUK/CDA/KDA/RDA and in other cases (if applicable)

Again, for HT/MT connection, customer submit the documents as per Citizen Charter which is available at DPDC website. Incomplete application will be informed to applicant immediately.

Step 3 : Applicant will be informed via SMS about site survey and that will be done within 3 days for LT connection whereas 5 days for HT/MT connection.

After the survey, Load will be allocated within 2 days for LT connection and 10 days for HT/MT connection.If there are any types discrepancy in survey report, applicant will be informed immediately.

Step 4 : Applicant will be requested to pay his/her due (if any) at the location of connection.

Step 5 : If applicant is qualified for new connection then he/she will be requested to pay estimated cost and security deposit according to type of connection immediately for LT connection.

In case of HT/MT connection this demand note will be issued within 2 days and customer should pay the same within 4 days.

Step 6 : Applicant should submit the bank deposit receipt to NOCS office.

Step 7 : Customer will be requested to submit meter and after successful testing of the meter it will be installed within 1 days for LT connection and 7 days for HT/MT connection.

3 Comments
Add a Comment
  1. Engr.G.M.Asraful Islam

    Application for New Connection in dhaka city , uttara

  2. Engr.G.M.Asraful Islam

    I want for Apply for New Connection

  3. Engr.G.M.Asraful Islam

    Application for New Connection

Leave a Reply to Engr.G.M.Asraful Islam Cancel reply

How to add comment : 1) Type your comment below. 2) Type your name. 3) Post comment.

www.statusin.org © 2021

Contact Us   Privacy Policy   Site Map